How to get a BABA waiver: the process, step by step

How to get a BABA waiver: identify the right category, build the evidence, and submit the request to your funding agency for OMB review. A clear walk-through of the five waiver types and what each one needs.

Reviewing paperwork at a desk to prepare a BABA waiver request
Photo by Anastassia Anufrieva on Unsplash

Learning how to get a BABA waiver starts with accepting what a waiver is not. It is not a pass, and it is not a box you tick. A Build America, Buy America waiver is a formal request that lets a non-compliant item proceed when a defined condition is met, and it only has effect once the funding agency grants it. Until then, the honest status of that line stays non-compliant. With that clear, here is the process end to end.

Step 1: Confirm the item really fails

Do not request a waiver for a line you have not actually tested. Run the determination first. Sometimes a component you assumed was foreign is domestic, or a percentage you feared was below 55 turns out to clear it. Only pursue a waiver once the calculator confirms a genuine shortfall.

Step 2: Pick the right category

There are five waiver categories, and choosing the wrong one wastes weeks. Each has a distinct trigger.

WaiverWhen it applies
Public interestApplying the requirement would be inconsistent with the public interest
NonavailabilityA compliant product is not produced in sufficient and reasonably available quantities or satisfactory quality
Unreasonable costA domestic option raises overall project cost by more than 25 percent
De minimisSmall non-compliant components below a defined share of total cost
Small grantsAwards below the Simplified Acquisition Threshold
The five BABA waiver categories and their triggers. Source: OMB M-24-02 and agency guidance.

The waivers overview covers each category in depth, and the individual pages, such as the nonavailability waiver, carry the specific tests.

Step 3: Assemble the evidence

A waiver request stands or falls on its evidence. A nonavailability case needs documented sourcing searches showing no compliant supplier at reasonable quantity or quality. An unreasonable cost case needs a clean comparison of the domestic and non-domestic figures that lands above the 25 percent line. Vague assertions get bounced; a well-evidenced file gets read.

A waiver may be granted where the head of the federal agency finds that a domestic product is not produced in sufficient and reasonably available quantities or of a satisfactory quality. (BABA nonavailability standard)

Step 4: Submit to the funding agency

You submit to the agency funding your project, not to OMB directly. The agency runs its own review, and for many waivers posts the proposed decision for public comment before finalising. OMB's Made in America Office coordinates across agencies to keep the bar consistent, which is why a thin request in one programme does not sail through just because a similar one did elsewhere.

Build the waiver timeline into your schedule. Because the request needs agency review, and sometimes a public comment window, it is not a same-week fix. Start early or you will be waiting on a decision at bid time.

Step 5: Proceed only once granted

This is the rule that protects you. Do not build the waiver into your certification as though it is already approved. If an auditor looks at the file before the decision lands, the line is non-compliant, full stop. Once the agency grants it in writing, keep that grant with the determination in the bid record.

A note on what a tool can and cannot do

Sourceory names the waiver category a non-compliant line may qualify for and cites the framework, so you know which door to knock on. It does not draft or file the waiver request for you; that is your submission to the agency. For the official route, agencies publish their waiver processes, and OMB lists government-wide guidance at the Made in America Office.

See which waiver category each non-compliant line may qualify for, cited to the framework.

Explore the waivers

Frequently asked questions

How do you get a BABA waiver?
Confirm the item is genuinely non-compliant, pick the right waiver category, assemble the supporting evidence, submit the request to your funding agency for review and OMB coordination, and only rely on the waiver once it is formally granted.
How long does a BABA waiver take?
It varies by agency and waiver type. Because many requests require agency review and sometimes a public comment window, it is not a same-week process, so build the timeline into your schedule.
What is the unreasonable cost waiver threshold?
The unreasonable cost waiver generally applies where using a domestic option would increase the overall project cost by more than 25 percent.
Can Sourceory file a waiver for me?
No. Sourceory identifies which waiver category a non-compliant line may qualify for and cites the framework, but the waiver request itself is your submission to the funding agency.

This guide is compliance guidance, not legal advice or a binding determination by any funding agency. To see the cited verdict for your own bill of materials, use the free BOM calculator, or see how the same engine works from your own code or an AI agent.