The de minimis waiver and the BABA 5 percent threshold
The BABA de minimis waiver lets small non-compliant components through under a defined share of total cost. Here is what the de minimis threshold covers, what it does not, and how it differs from the 55 percent test.
The de minimis waiver is one of the most searched and most misunderstood corners of Build America, Buy America. In plain terms, it recognises that chasing the origin of every tiny, low-cost component would be disproportionate, so it allows a small share of non-compliant material through. The trouble is that people stretch it well past what it covers. This guide sets out what the de minimis threshold actually does, and what it does not.
What de minimis is for
De minimis exists to keep the rules workable. A project can contain countless minor items, and requiring a full origin trace on a handful of low-value parts would cost more than it protects. The de minimis waiver lets those minor non-compliant components through provided they stay under a defined portion of total cost. It is applied as a general allowance rather than something you argue case by case.
A de minimis waiver allows for a limited amount of non-compliant components below a defined percentage of the total cost of the project's materials. (BABA waiver framework, summarised)
What it is not
Here is the misunderstanding to avoid. De minimis is not a back door around the 55 percent manufactured-products test. You cannot take a manufactured product that lands at, say, 50 percent domestic content and wave it through as de minimis. The two rules answer different questions: the 55 percent test decides whether a manufactured product is domestic, while de minimis is a project-level allowance for genuinely minor items.
| Rule | Question it answers | Scope |
|---|---|---|
| 55 percent threshold | Is this manufactured product domestic? | Per product, on component cost |
| De minimis waiver | Can minor non-compliant items be overlooked? | Project-level, small share of total cost |
A single component being cheap does not make it de minimis. The allowance is about the aggregate share of minor non-compliant material at the project level, not about excusing one part because its own line looks small.
Where the boundaries sit
Because de minimis is applied as a general waiver, the exact figure and how it is measured come from the governing guidance rather than from a number you set. Read it against your funding agency's current position, and do not assume a threshold you half-remember. Our waivers overview covers where de minimis sits among the five categories, and the de minimis waiver page carries the detail the ruleset holds.
How to use it without overreaching
Treat de minimis as the last, small tidy-up after you have done the real work, not as a strategy. Classify every item, run the 55 percent math on manufactured products, and resolve genuine shortfalls through the proper waiver. If a modest residue of truly minor non-compliant material remains, that is where de minimis belongs. For the governing rules, OMB's Made in America Office is the authority.
Run a full determination first, and see exactly which lines are genuinely minor and which need a real answer.
Run the calculatorFrequently asked questions
- What is the de minimis waiver under BABA?
- It is a general applicability waiver that lets a small share of minor non-compliant components through when they fall under a defined portion of the total cost of the project's materials, so that tracing every low-value part is not required.
- Can de minimis rescue a manufactured product that fails the 55 percent test?
- No. De minimis is a project-level allowance for minor items. It does not override the 55 percent domestic-content test that decides whether a manufactured product is domestic.
- Is a cheap component automatically de minimis?
- No. The allowance is about the aggregate share of minor non-compliant material at the project level, not about excusing an individual part because its own line looks small.
- How do I find the exact de minimis threshold?
- Because it is applied as a general waiver, the exact figure and measurement come from the governing OMB and agency guidance. Confirm it against your funding agency's current position rather than a remembered number.
This guide is compliance guidance, not legal advice or a binding determination by any funding agency. To see the cited verdict for your own bill of materials, use the free BOM calculator, or see how the same engine works from your own code or an AI agent.
More guides
Put this into practice on your own BOM
Check a bill of materials free in your browser, cited to the OMB and agency source.